US Steel has idled a second blast furnace at its Košice steelworks in Slovakia.

US Steel

The No. 1 BF at Košice has been temporarily idled as of Dec. 2 “as a result of very high energy prices, low market demand and surging imports,” a US Steel spokeswoman confirmed to SMU in an email Tuesday, Dec. 6.

In September, the company pulled forward a 60-day planned outage on the No. 2 Košice BF. That furnace has remained down, awaiting an improvement in customer activity.

“We expect to resume two BF operations at the beginning of 2023,” the spokeswoman added.

A third BF at the carbon flat-rolled, electrical steel, and spiral-weld pipe mill remains in operation.

In its third quarter earnings conference call in late October, executives of the Pittsburgh-based steelmaker commented on the challenging environment it has been facing in Europe. President and CEO David Burritt said on the call the company would continue to adjust to manage the headwinds of high raw material and energy costs, buyer destocking, and the continuing war in neighboring Ukraine.

By Laura Miller, Laura@SteelMarketUpdate.com

Laura Miller

Read more from Laura Miller

Latest in Final Thoughts

Final Thoughts

It’s been another week of torrid speculation when it comes Trump and tariffs. And another week of mostly flat price movement when it comes to steel sheet and plate. As far as Trump and tariffs go, I think I might have lost track. We've potentially got 10% blanket tariffs on imports from China, 25% tariffs on imports from Canada and Mexico, 100% tariffs on the BRICs, and 200% on Caterpillar. Canada might be the 51st state. Mexico could be the 52nd state. But all can be resolved if you stop by Mar-a-Lago and kiss the ring?