Steel Mills
USS's Mon Valley No. 3 BF Could Stay Idled Through November
Written by David Schollaert
September 22, 2022
US Steel Corp.’s month-long maintenance outage on the No. 3 blast furnace at Mon Valley Works near Pittsburgh is expected to be completed on Saturday, Sept. 24, a company spokeswoman confirmed to SMU.
Once complete, the blast furnace is expected to remain idle for the next month or so in response to declining demand and market conditions, sources familiar with the matter told SMU.
When asked for comment on the potential idling, US Steel said that “market conditions will dictate if it is restarted.”
The blast furnace was taken offline on Aug. 30—pulled forward by more than a month—for shotcrete (sprayed concrete) reline and maintenance, a significantly shorter and less expensive process than a full reline.
Mon Valley Works has two blast furnaces: No. 1 and No. 3. The No. 1 furnace has a daily ironmaking capacity of approximately 3,200 tons. The No. 3 furnace has a daily capacity of approximately 2,900 tons.
The furnaces are located at US Steel’s Edgar Thomson plant in Braddock, Pa. That facility makes slabs and rails them to the company’s Irvin Plant in West Mifflin, Pa., where they are rolled into sheet.
If the latest idling stands true, this would be the third in a series of idlings this month, following the temporary idling of the No. 5 tin line and the No. 8 blast furnace at Gary Works in Indiana.
The Pittsburgh-based steelmaker has said weaker demand and increased imports were to blame for the two temporary idlings.
The potential idling of No. 3 at Mon Valley Works comes on the back of lower third-quarter earnings guidance—down nearly 50% sequentially and 60% year-on-year—while negotiations for a new labor contract between the steelmaker and the United Steelworkers union seem to be at an impasse, according to a Sept. 16 USW bargaining update.
By David Schollaert, David@SteelMarketUpdate.com
David Schollaert
Read more from David SchollaertLatest in Steel Mills
USS/Nippon deal: Who will have the happiest holidays?
Will Santa bring gifts for the leadership, employees, and shareholders of U.S. Steel and Nippon Steel, and lumps of coal for USW leadership and politicians opposed to the deal?
‘Orderly liquidation’ of AHMSA assets begins
A trustee has formally taken over AHMSA and begun the liquidation process of the bankrupt Mexican steelmaker.
Nippon buying stake in Canadian iron ore project
Nippon Steel and a Japanese trading company have entered an agreement to buy a 49% interest in a Champion Iron ore project in Canada.
USS anticipates Q4 loss on weak demand, BR2 start-up
Amid a challenging pricing and demand environment, and with the ongoing ramp-up of the Big River 2 mill, USS is anticipating a loss for the fourth quarter.
Nucor blames steel mills segment for depressed Q4 guidance
Nucor cited decreased volumes and prices in it steel mills segment as the key driver of its lower guidance for the fourth quarter.