Steel Mills

USS's Mon Valley No. 3 BF Could Stay Idled Through November
Written by David Schollaert
September 22, 2022
US Steel Corp.’s month-long maintenance outage on the No. 3 blast furnace at Mon Valley Works near Pittsburgh is expected to be completed on Saturday, Sept. 24, a company spokeswoman confirmed to SMU.
Once complete, the blast furnace is expected to remain idle for the next month or so in response to declining demand and market conditions, sources familiar with the matter told SMU.
When asked for comment on the potential idling, US Steel said that “market conditions will dictate if it is restarted.”
The blast furnace was taken offline on Aug. 30—pulled forward by more than a month—for shotcrete (sprayed concrete) reline and maintenance, a significantly shorter and less expensive process than a full reline.
Mon Valley Works has two blast furnaces: No. 1 and No. 3. The No. 1 furnace has a daily ironmaking capacity of approximately 3,200 tons. The No. 3 furnace has a daily capacity of approximately 2,900 tons.
The furnaces are located at US Steel’s Edgar Thomson plant in Braddock, Pa. That facility makes slabs and rails them to the company’s Irvin Plant in West Mifflin, Pa., where they are rolled into sheet.
If the latest idling stands true, this would be the third in a series of idlings this month, following the temporary idling of the No. 5 tin line and the No. 8 blast furnace at Gary Works in Indiana.
The Pittsburgh-based steelmaker has said weaker demand and increased imports were to blame for the two temporary idlings.
The potential idling of No. 3 at Mon Valley Works comes on the back of lower third-quarter earnings guidance—down nearly 50% sequentially and 60% year-on-year—while negotiations for a new labor contract between the steelmaker and the United Steelworkers union seem to be at an impasse, according to a Sept. 16 USW bargaining update.
By David Schollaert, David@SteelMarketUpdate.com

David Schollaert
Read more from David SchollaertLatest in Steel Mills

Nippon could up investment in USS facilities to $7B: Report
It's the latest twist as the proxy battle heats up for Pittsburgh-based U.S. Steel.

Hybar expansion still on the table as Arkansas mill startup nears
As Hybar nears the completion of its $700-million rebar mill in Arkansas, the company said it is still “actively considering” building other steel facilities in the southern US.

Global steel production edges lower in February
February’s global raw steel output is tied with last December's for the fourth-lowest monthly production rate recorded over the past two years.

Fate of U.S. Steel hangs in the balance
The future of U.S. Steel remains unclear, but the proxy fight for control of the company is heating up. Shareholders will cast their votes on the company's future at the annual meeting in May.

Cliffs to idle Dearborn blast furnace, restart Cleveland furnace by July
Cleveland-Cliffs has decided to idle the steelmaking operations at its Dearborn Works in Michigan due to weak automotive demand.