Phase 2 of Algoma Plate Mill Upgrades Pushed to June 2023
Written by Michael Cowden
August 9, 2022
Algoma’s plate mill is up and running following the first phase of a modernization project that was completed in June.
The second phase of the expansion, initially expected to be finished by November 2022, has been moved to June 2023, a company spokeswoman told SMU on Tuesday, Aug. 9.
The reason: “to support our customers impacted by a longer-than-anticipated outage due to automation issues during the first phase,” she said.
Algoma had scheduled a one-month outage in its fiscal first quarter, which ended in June, to complete the first phase of upgrades. It took the steelmaker approximately six to eight weeks longer than expected to start up the mill following the outage, company executives said on an earnings conference call with analysts last week.
The protracted start-up resulted from problems with automation equipment installed as part of the upgrades. The result: Production and shipment volumes in both the first and second quarters of Algoma’s fiscal year are expected to be lower than in the same quarters last year, they said.
Algoma makes hot-rolled coil, cold-rolled coil, and plate. Company executives noted that the outage and delayed start-up of the plate mill would impact not only discrete plate volumes but also those of strip mill plate too.
SMU’s plate price averaged $1,735 per ton ($86.75 per cwt) when this article was filed, down 3.6% from $1,800 per ton a month earlier on the heels of a price decrease announced by Charlotte, N.C.-based Nucor Corp.
By Michael Cowden, Michael@SteelMarketUpdate.com

Michael Cowden
Read more from Michael CowdenLatest in Steel Mills

Nippon could up investment in USS facilities to $7B: Report
It's the latest twist as the proxy battle heats up for Pittsburgh-based U.S. Steel.

Hybar expansion still on the table as Arkansas mill startup nears
As Hybar nears the completion of its $700-million rebar mill in Arkansas, the company said it is still “actively considering” building other steel facilities in the southern US.

Global steel production edges lower in February
February’s global raw steel output is tied with last December's for the fourth-lowest monthly production rate recorded over the past two years.

Fate of U.S. Steel hangs in the balance
The future of U.S. Steel remains unclear, but the proxy fight for control of the company is heating up. Shareholders will cast their votes on the company's future at the annual meeting in May.

Cliffs to idle Dearborn blast furnace, restart Cleveland furnace by July
Cleveland-Cliffs has decided to idle the steelmaking operations at its Dearborn Works in Michigan due to weak automotive demand.