JSW Steel USA has begun to recall workers at its idled sheet mill in Mingo Junction, Ohio, as well as at its idled plate and pipe mills in Baytown, Texas, the company’s top executive said.
“We still intend to start up both facilities in March,” JSW Steel USA CEO Mark Bush told Steel Market Update in an email on Monday.
JSW Steel USA idled its Mingo Junction and Baytown mills in 2020 in response to poor market demand. It also took the downtime to make upgrades to the Ohio mill’s electric-arc furnace (EAF) and caster.
The idling of Mingo Junction contributed to a severe spot market squeeze in the second half of 2020, a period that saw steel prices soar from less than $25/cwt ($500 per ton) to more than $50/cwt ($1,000 a ton). A restart of the facility could help to ease that squeeze.
The Mingo Junction mill’s EAF has annual capacity of 1.5 million tons per year, according to the Association for Iron and Steel Technology’s 2020 directory of iron and steel plants. It also sports a ladle metallurgy furnace (LMF), a slab caster and an 80-inch hot-strip mill, according to the company’s website.
The Baytown mill does not have an EAF and so relies on its sister mill in Ohio or on imported slabs for substrate to roll into plate and pipe.
Industry sources have told Steel Market Update that JSW is bringing in imported slab from southern Ohio to Mingo Junction, which might allow it to restart the HSM ahead of the EAF. Bush did not comment on that issue.
By Michael Cowden, michael@steelmarketupdate.com
Michael Cowden
Read more from Michael CowdenLatest in Steel Mills
USS confirms split CFIUS decision on Nippon deal; it’s now up to Biden
Nippon Steel's purchase of U.S. Steel could lead to lower steel output domestically, and that presents “a national security risk," the Washington Post reported.
USS/Nippon deal: Who will have the happiest holidays?
Will Santa bring gifts for the leadership, employees, and shareholders of U.S. Steel and Nippon Steel, and lumps of coal for USW leadership and politicians opposed to the deal?
‘Orderly liquidation’ of AHMSA assets begins
A trustee has formally taken over AHMSA and begun the liquidation process of the bankrupt Mexican steelmaker.
Nippon buying stake in Canadian iron ore project
Nippon Steel and a Japanese trading company have entered an agreement to buy a 49% interest in a Champion Iron ore project in Canada.
USS anticipates Q4 loss on weak demand, BR2 start-up
Amid a challenging pricing and demand environment, and with the ongoing ramp-up of the Big River 2 mill, USS is anticipating a loss for the fourth quarter.