Steel Mills

SDI To Commission Four Value-Add Lines Before End of Q1’24
Written by Laura Miller
October 19, 2023
Steel Dynamics Inc. provided an update on the four new coating lines it is adding to its Heartland flat-rolled processing mill and Sinton sheet mill on its third-quarter earnings conference call with analysts on Thursday, Oct. 19. The projects were originally announced in 2021.
SDI Heartland
The new painting and galvanizing lines at SDI Heartland in Terre Haute, Ind., could be up and running by the end of the year, EVP and CFO Theresa Wagler said on the call. If not by year’s end, then early in the first quarter of 2024.
The new Heartland galvanizing line will be able to process 300,000 tons per year of flat-rolled steel and will also have Galvalume coating capabilities. The new paint line will have a capacity of 240,000 tons per year.
The Heartland mill currently has the capacity to produce 1 million tons of cold-rolled steel, with galvanizing capacity of 360,000 tons, according to SDI’s website. SDI purchased the mill in 2018 from CSN for $400 million.
SDI Sinton
Sinton’s new paint and galvanizing lines are now anticipated to be commissioned shortly after the Heartland lines in Q1’24, SDI’s chairman and CEO Mark Millett said on the call.
The $225-million project is adding a 300,000-ton-per-year flat-rolled galvanizing line, also with Galvalume coating capabilities, and a 240,000-ton-per-year paint line.
The startup of the Sinton, Texas, mill has not been without issue. The mill was originally announced in 2019, and construction began early in 2020. At that time, operations were expected to begin by mid-2021. Startup of the hot end was delayed for various reasons, including severe flooding, but occurred early in 2022. This year, the mill had an unplanned outage for the entire month of July due to caster shear equipment issues. The outage resulted in an estimated 90,000 tons of lost production.

Laura Miller
Read more from Laura MillerLatest in Steel Mills

Nippon could up investment in USS facilities to $7B: Report
It's the latest twist as the proxy battle heats up for Pittsburgh-based U.S. Steel.

Hybar expansion still on the table as Arkansas mill startup nears
As Hybar nears the completion of its $700-million rebar mill in Arkansas, the company said it is still “actively considering” building other steel facilities in the southern US.

Global steel production edges lower in February
February’s global raw steel output is tied with last December's for the fourth-lowest monthly production rate recorded over the past two years.

Fate of U.S. Steel hangs in the balance
The future of U.S. Steel remains unclear, but the proxy fight for control of the company is heating up. Shareholders will cast their votes on the company's future at the annual meeting in May.

Cliffs to idle Dearborn blast furnace, restart Cleveland furnace by July
Cleveland-Cliffs has decided to idle the steelmaking operations at its Dearborn Works in Michigan due to weak automotive demand.