In line with the declining steel prices, lead times for spot orders from the mills continue to shorten with the average for hot rolled now below five weeks and cold rolled and galvanized now below eight weeks, based on Steel Market Update’s check of the market on Monday and Tuesday. Lead times for all products are the shortest they have been in 2021 and are comparable to where they were in September/October 2020. Lead times are a sign of activity at the mill level and are considered a leading indicator of finished steel prices.
Buyers polled by SMU this week reported mill lead times ranging from 3-9 weeks for hot rolled, 5-10 weeks for cold rolled, 5-11 weeks for galvanized, 8-10 weeks for Galvalume, and 4-6 weeks for plate.
The average lead time for hot rolled has declined to 4.92 weeks from 5.04 weeks in mid-December. Cold rolled lead times now average 7.53 weeks, a decline from 8.35 two weeks ago. Galvanized lead times dipped to 7.50 weeks from 8.19 weeks in the same period. The average Galvalume lead time remains about the same at 8.83 weeks.
Like sheet products, mill lead times for plate also continue to shorten. The average plate lead time moved down to 5.40 weeks from the 6.38 weeks seen in SMU’s market check two weeks ago.
To put those numbers in perspective, hot rolled lead times have averaged 4.59 weeks, cold rolled lead times 6.59 weeks and galvanized lead times 6.92 weeks in data gathered by SMU over the past decade. Therefore, lead times are now within a week of being what might be considered “normal” after a long period of historic highs.
By Tim Triplett, Tim@SteelMarketUpdate.com
Tim Triplett
Read more from Tim TriplettLatest in SMU Data and Models
Apparent steel supply eases in August
The volume of finished steel entering the US market declined in August from July, according to SMU’s analysis of data from the US Department of Commerce and the American Iron and Steel Institute (AISI). Referred to as ‘apparent steel supply,’ we calculate this monthly rate by combining domestic steel mill shipments and finished US steel imports and deducting total US steel exports.
September service center shipments and inventories report
Flat rolled = 60.8 shipping days of supply Plate = 52.7 shipping days of supply Flat rolled Flat-rolled steel supply at US service centers declined in September, though still seasonally high. September’s report reflects lower demand, stable lead times, and restocking early in the third quarter at a perceived bottom in prices. At the end […]
SMU market survey results now available
SMU’s latest steel buyers market survey results are now available on our website to all premium members. After logging in at steelmarketupdate.com, visit the pricing and analysis tab and look under the “survey results” section for “latest survey results.” Past survey results are also available under that selection. If you need help accessing the survey results, or if […]
SMU survey: Steel Buyers’ Sentiment Indices diverge
SMU’s Steel Buyers’ Sentiment Indices moved in different directions this week. Our Current Steel Buyers’ Sentiment Index eased to a six-week low, while Future Buyers’ Sentiment ticked up to a four-week high. Both of our Indices continue to indicate optimism among steel buyers.
SMU survey: Mill lead times stretch out marginally
Steel mill lead times inched up this week for most sheet and plate products, according to buyers responding to our latest market survey.