Integrated steelmaker U.S. Steel is taking the No. 6 blast furnace at its Gary Works steel mill offline for 38 days beginning at the end of next month, a company spokesperson confirmed to Steel Market Update.
The planned maintenance outage at its Indiana facility is scheduled for Sept. 30 and should run through Nov. 9. This is the first lengthier outage to the furnace since it was idled for two months because of COVID-19-related closures in April 2020.
The scope of work to the 1.23-million-ton-per-year furnace includes repairs and replacement of the hot blast system and furnace top equipment, said the U.S. Steel spokesperson.
This extensive outage to No. 6 coincides with U.S. Steel’s week-long maintenance program scheduled for its Big River Steel operations during Q4.
This latest outage enters the queue of fourth-quarter maintenance programs across North American steelmakers. In addition to U.S. Steel’s planned outages, Cleveland-Cliffs’ Indiana Harbor No. 7 blast furnace will be offline for approximately 45 days, while Nucor’s Gallatin, Ky., flat-rolled mill will undergo maintenance on its electric-arc furnace for roughly 30 days at the end of November.
By David Schollaert, David@SteelMarketUpdate.com
David Schollaert
Read more from David SchollaertLatest in Steel Mills
‘Orderly liquidation’ of AHMSA assets begins
A trustee has formally taken over AHMSA and begun the liquidation process of the bankrupt Mexican steelmaker.
Nippon buying stake in Canadian iron ore project
Nippon Steel and a Japanese trading company have entered an agreement to buy a 49% interest in a Champion Iron ore project in Canada.
USS anticipates Q4 loss on weak demand, BR2 start-up
Amid a challenging pricing and demand environment, and with the ongoing ramp-up of the Big River 2 mill, USS is anticipating a loss for the fourth quarter.
Nucor blames steel mills segment for depressed Q4 guidance
Nucor cited decreased volumes and prices in it steel mills segment as the key driver of its lower guidance for the fourth quarter.
SDI warns of lower Q4 profits on weak prices, Butler outage
The Fort Wayne, Ind.-based steelmaker and metal recycler expects Q4'24 earnings guidance in the range of $1.26 to $1.30 per diluted share.