Big River Steel plans to take a week-long plant-wide maintenance outage in October at its mill in Osceola, Ark., a company spokeswoman confirmed.
The planned outage, for normal preventative maintenance and mill reliability, is scheduled to start on Oct. 10, she said.
The scheduled maintenance includes both electric-arc furnaces (EAFs)—with annual production capacity of 3.3 million tons of flat rolled steel—as well as the casting, heating, and rolling lines.
Although the weeklong maintenance outage is slated for early Q4, lead times are presently 8-12 weeks out and the disruption may be felt by a tight marketplace.
Big River Steel makes hot-rolled, cold-rolled, pickled, electrical, and hot-dipped galvanized steels for a wide range of downstream industries, including automotive, appliance and distribution.
By David Schollaert, David@SteelMarketUpdate.com
David Schollaert
Read more from David SchollaertLatest in Steel Mills
‘Orderly liquidation’ of AHMSA assets begins
A trustee has formally taken over AHMSA and begun the liquidation process of the bankrupt Mexican steelmaker.
Nippon buying stake in Canadian iron ore project
Nippon Steel and a Japanese trading company have entered an agreement to buy a 49% interest in a Champion Iron ore project in Canada.
USS anticipates Q4 loss on weak demand, BR2 start-up
Amid a challenging pricing and demand environment, and with the ongoing ramp-up of the Big River 2 mill, USS is anticipating a loss for the fourth quarter.
Nucor blames steel mills segment for depressed Q4 guidance
Nucor cited decreased volumes and prices in it steel mills segment as the key driver of its lower guidance for the fourth quarter.
SDI warns of lower Q4 profits on weak prices, Butler outage
The Fort Wayne, Ind.-based steelmaker and metal recycler expects Q4'24 earnings guidance in the range of $1.26 to $1.30 per diluted share.