Big River Steel plans to take a week-long plant-wide maintenance outage in October at its mill in Osceola, Ark., a company spokeswoman confirmed.
The planned outage, for normal preventative maintenance and mill reliability, is scheduled to start on Oct. 10, she said.
The scheduled maintenance includes both electric-arc furnaces (EAFs)—with annual production capacity of 3.3 million tons of flat rolled steel—as well as the casting, heating, and rolling lines.
Although the weeklong maintenance outage is slated for early Q4, lead times are presently 8-12 weeks out and the disruption may be felt by a tight marketplace.
Big River Steel makes hot-rolled, cold-rolled, pickled, electrical, and hot-dipped galvanized steels for a wide range of downstream industries, including automotive, appliance and distribution.
By David Schollaert, David@SteelMarketUpdate.com
David Schollaert
Read more from David SchollaertLatest in Steel Mills
Algoma to shut down line in Ontario ahead of EAF start
The 106” Mill was part of Algoma's plate and strip combination facility.
Nippon trial vs. US government to begin early next month: Report
Nippon Steel’s litigation against the US government is set to begin in early February, according to a report by Japan’s Kyodo News Agency. Nippon will file its opening brief on Feb. 3. And both parties will conclude their claims by March 17 in the US Court of Appeals for the District of Columbia Circuit, Kyodo […]
Nucor carbon targets certified by GSCC
Nucor’s “ambitious” carbon targets by the end of the decade and beyond have been certified by the Global Steel Climate Council (GSCC). The Charlotte, N.C.-based steelmaker used a base year of 2023 for its science-based emissions targets (SBET). It set an SBET of 0.975 metric tons (mt) of CO2 emissions per mt of hot-rolled steel […]
SSAB halts talks with Feds on Miss. green steel plant
The Department of Energy's Industrial Demonstrations Program page states that it is no longer moving forward with SSAB.
Cleveland-Cliffs CEO seeks ‘American solution’ for U.S. Steel
He said a new entity would operate under the U.S. Steel name and would retain its Pittsburgh headquarters.