Steel Mills

Big River Steel Ramp-Up Plan

Written by John Packard


There is a new flat rolled steel mill under construction in Arkansas. The mill will be complete in 2016. However, we feel that many of you are probably interested to know what the timetable is for the ramp up of the mill at this point in time.

We have obtained the ramp-up schedule from Big River Steel with the ready dates for specific products:

Latest in Steel Mills

USS threatens to cut ‘thousands’ of jobs, move HQ if Nippon sale blocked

U.S. Steel could slash thousands of jobs, shift away from integrated steelmaking, and move its headquarters out of Pittsburgh if its acquisition by Nippon Steel isn’t completed, the company’s top executive said. “We want elected leaders and other key decision makers to recognize the benefits of the deal was well as the unavoidable consequences if the deal fails,” company President and CEO David Burritt said in a statement on Wednesday.